BMO Convention and Trade Centre Expansion

Calgary, Alberta

completeTourismNRP
Federal contribution
$166.4M
$166,355,005
Federal share33%

of $500.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2019
201920202021202220232024
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Apr 10, 2019(actual)
Construction end
Mar 13, 2024(actual)

Against the original forecast

  • Construction end4 months earlyforecast Jun 30, 2024