Calgary Ring Road
Federal contribution
$100.0M
$100,000,000
Federal share17%
of $575.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 22, 2009
ApprovedMar 31, 2010
20102011201220132014
Built
Approved 10 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Alberta
- Construction start
- Jun 7, 2010(actual)
- Construction end
- Nov 22, 2013(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2014
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29911 in the federal list. How to read these figures.