Sewer Upgrade

Moose Jaw, Saskatchewan

completeWastewaterMRIF
Federal contribution
$175,000
Federal share6%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
20072008
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Moose Jaw
Construction start
Jan 3, 2007(actual)
Construction end
Feb 21, 2008(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end6 weeks earlyforecast Mar 31, 2008