Back to projects

Evergreen Brick Works

Toronto, Ontario

completeRecreationCSIF
Federal contribution
$20.0M
$20,000,000
Federal share44%

of $45.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 20, 2006
ApprovedJul 20, 2007
20072008200920102011
Built

Approved 7 months after the announcement.

Program
Canada Strategic Infrastructure Fund
Ultimate recipient
Evergreen
Construction start
Dec 1, 2008(actual)
Construction end
Dec 20, 2010(actual)

Also in Toronto