Evergreen Brick Works
Federal contribution
$20.0M
$20,000,000
Federal share44%
of $45.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 20, 2006
ApprovedJul 20, 2007
20072008200920102011
Built
Approved 7 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Evergreen
- Construction start
- Dec 1, 2008(actual)
- Construction end
- Dec 20, 2010(actual)
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17240 in the federal list. How to read these figures.