Water Supply Improvements

Admirals Beach, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$65,282
Federal share12%

of $541.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20092011201320152017
Built

Approved 7.3 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Admiral's Beach
Construction start
Dec 15, 2008(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start5 months earlyforecast May 1, 2009
  • Construction end7.5 years lateforecast Oct 1, 2009

Also in Admirals Beach

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17255 in the federal list. How to read these figures.