Water Tank Upgrade

Admirals Beach, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$273,804
Federal share31%

of $884.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2018
201920202021202220232024
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Admirals Beach
Construction start
Jun 23, 2023(actual)
Construction end
Nov 9, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 23, 2023
  • Construction end3 months lateforecast Aug 1, 2023

Also in Admirals Beach

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52236 in the federal list. How to read these figures.