Back to projects

Asset Management

Amherstburg, Ontario

completeCapacity BuildingMRIF
Federal contribution
$6,383
Federal share33%

of $19.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 4, 2007
200720082009
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Amherstburg
Construction start
Jun 6, 2007(actual)
Construction end
Mar 12, 2009(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Mar 31, 2009