Asset Management
Federal contribution
$6,383
Federal share33%
of $19.1K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 4, 2007
200720082009
Built
Approved 5 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Amherstburg
- Construction start
- Jun 6, 2007(actual)
- Construction end
- Mar 12, 2009(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Mar 31, 2009
Also in Amherstburg
- Construction of the Amherstburg Multi-Use Recreation Complex$7.8M
- Upgrading of the Amherstburg Pollution Control Plant$5.3M
- Edgewater Sewage Diversion$2.9M
- Pump Station Upgrades, Forcemain Installation and Edgewater Lagoon Decommissioning$2.5M
- Amherstburg Water Treatment Plant Reservoir Rehabilitation$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17278 in the federal list. How to read these figures.