County of Brant Asset Management

Burford, Ontario

completeCapacity BuildingMRIF
Federal contribution
$10,383
Federal share33%

of $31.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 7, 2007
2007200820092010
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Brant
Construction start
May 15, 2007(actual)
Construction end
Oct 31, 2010(actual)