Construction of a Community Centre

Burford, Ontario

completeRecreationCC
Federal contribution
$6.4M
$6,405,204
Federal share33%

of $19.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
200920102011201220132014
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Brant
Construction start
Aug 20, 2009(actual)
Construction end
Sep 9, 2014(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2014

Also in Burford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24673 in the federal list. How to read these figures.