Lantzville Sanitary Sewer Collection System - Phase 2

Lantzville, British Columbia

completeWastewaterMRIF
Federal contribution
$1.5M
$1,468,165
Federal share31%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 19, 2007
20082009201020112012
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
District of Lantzville
Construction start
Sep 4, 2007(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 21, 2007