Phase III Sanitary Sewer Collection System
Federal contribution
$2.2M
$2,186,666
Federal share33%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 11, 2017
2018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- District of Lantzville
- Construction start
- Apr 6, 2020(actual)
- Construction end
- Apr 30, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 2, 2020
- Construction end2 months earlyforecast Jun 30, 2021
Also in Lantzville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49724 in the federal list. How to read these figures.