Port Hardy - Wastewater Lift Station Upgrades
Federal contribution
$409,666
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2008
2008200920102011
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- District of Port Hardy
- Construction start
- Dec 12, 2007(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 19, 2007
Also in Port Hardy
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17507 in the federal list. How to read these figures.