Port Hardy - Recreation Revitalization (Arena)
Federal contribution
$1.8M
$1,788,772
Federal share60%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- District of Port Hardy
- Construction start
- Aug 10, 2020(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2020
Also in Port Hardy
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56221 in the federal list. How to read these figures.