Sicamous - Two Mile Area Water Extensions
Federal contribution
$227,000
Federal share33%
of $681.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2008
2008200920102011
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- District of Sicamous
- Construction start
- Dec 12, 2007(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 19, 2007
- Construction end12 months earlyforecast Mar 31, 2012