Highway 1 - North Fork Bridge
Federal contribution
$8.9M
$8,895,992
Federal share49%
of $18.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 24, 2016
20172018
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of British Columbia
- Construction start
- Oct 11, 2016(actual)
- Construction end
- Sep 14, 2018(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Oct 31, 2016
- Construction end7 weeks earlyforecast Oct 31, 2018
Also in Sicamous
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46644 in the federal list. How to read these figures.