Wastewater Facilities Upgrades

Sicamous, British Columbia

completeWastewaterCWWF
Federal contribution
$970,477
Federal share50%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Apr 26, 2017(actual)
Construction end
Jun 29, 2018(actual)

Against the original forecast

  • Construction start4 months earlyforecast Sep 5, 2017
  • Construction end9 months earlyforecast Mar 31, 2019

Also in Sicamous

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49761 in the federal list. How to read these figures.