Kent - Agassiz Wastewater Treatment Plant Upgrades
Federal contribution
$237,966
Federal share33%
of $713.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 21, 2008
200820092010
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- District of Kent
- Construction start
- Dec 12, 2007(actual)
- Construction end
- Mar 31, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 19, 2007