Kent - Hammersley Pump Station Upgrade: Floodbox Construction

Agassiz, British Columbia

completeWastewaterCC
Federal contribution
$165,000
Federal share33%

of $495.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2012
201220132014
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
District of Kent
Construction start
Jan 1, 2013(actual)
Construction end
Mar 31, 2014(actual)

Also in Agassiz

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41705 in the federal list. How to read these figures.