Schedule

AnnouncedDec 6, 2006
ApprovedMay 4, 2007
2007200820092010
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Enniskillen
Construction start
May 4, 2007(actual)
Construction end
Dec 15, 2009(actual)

Against the original forecast

  • Construction end11 months earlyforecast Oct 31, 2010