Back to projects

Town of New Tecumseth - Asset Management

Alliston, Ontario

completeCapacity BuildingMRIF
Federal contribution
$7,237
Federal share33%

of $21.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 26, 2007
20072008
Built

Approved 7 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of New Tecumseth
Construction start
Jun 26, 2007(actual)
Construction end
Mar 29, 2008(actual)

Against the original forecast

  • Construction end12 months earlyforecast Mar 31, 2009