Back to projects

Restoration of the Monument Building

Alliston, Ontario

completeCultureCC
Federal contribution
$65,934
Federal share33%

of $197.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of New Tecumseth
Construction start
Apr 27, 2009(actual)
Construction end
Dec 15, 2009(actual)

Also in Alliston