Major waterworks upgrades in Salaberry-de-Valleyfield
Salaberry-de-Valleyfield, Quebec
Federal contribution
$3.5M
$3,497,091
Federal share24%
of $14.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 28, 2008
200820092010201120122013
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Salaberry-De-Valleyfield
- Construction start
- May 28, 2008(actual)
- Construction end
- Dec 31, 2012(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 1, 2008
- Construction end21 months lateforecast Mar 31, 2011
Also in Salaberry-de-Valleyfield
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17791 in the federal list. How to read these figures.