Water Systems Upgrades

Salaberry-de-Valleyfield, Quebec

completeWastewaterGIS
Federal contribution
$1.8M
$1,799,958
Federal share40%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 26, 2021(actual)
Construction end
May 26, 2022(actual)

Against the original forecast

  • Construction start11 months earlyforecast Apr 4, 2022
  • Construction end13 months earlyforecast Jun 30, 2023

Also in Salaberry-de-Valleyfield

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56693 in the federal list. How to read these figures.