County of Hastings - Asset Management

Belleville, Ontario

completeCapacity BuildingMRIF
Federal contribution
$9,060
Federal share33%

of $27.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Hastings
Construction start
Jun 18, 2007(actual)
Construction end
Apr 9, 2009(actual)

Also in Belleville