Manitoba Floodway Expansion (Phase 1)
Federal contribution
$120.0M
$120,000,000
Federal share50%
of $240.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedFeb 23, 2003
ApprovedDec 8, 2003
2003200620092012
Built
Approved 9 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Manitoba Floodway Authority
- Construction start
- Sep 23, 2005(actual)
- Construction end
- Mar 18, 2014(actual)
Against the original forecast
- Construction start2 years lateforecast Sep 23, 2003
- Construction end12 months earlyforecast Mar 31, 2015
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17834 in the federal list. How to read these figures.