Transition to Zero-Emission Buses

Winnipeg, Manitoba

underwayPublic TransitPTIS
Federal contribution
$110.7M
$110,655,200
Federal share40%

of $276.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 8, 2022
today
202320242025202620272028
BuiltForecast

Approved 2 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Winnipeg
Construction start
Dec 1, 2022(actual)
Construction end
Apr 30, 2028(forecast)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 1, 2022