Brockville Asset Management

Brockville, Ontario

completeCapacity BuildingMRIF
Federal contribution
$5,400
Federal share33%

of $16.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Brockville
Construction start
Jun 18, 2007(actual)
Construction end
Oct 12, 2009(actual)

Against the original forecast

  • Construction end6 months earlyforecast Mar 31, 2010

Also in Brockville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17921 in the federal list. How to read these figures.