Schedule
AnnouncedDec 6, 2006
ApprovedMay 24, 2007
2007
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Central Frontenac
- Construction start
- Jun 1, 2007(actual)
- Construction end
- Nov 21, 2007(actual)
Against the original forecast
- Construction end13 months earlyforecast Dec 21, 2008