Revitalization of Playground at Oso Beach
Federal contribution
$16,950
Federal share33%
of $50.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Central Frontenac
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Apr 30, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2009
Also in Sharbot Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27723 in the federal list. How to read these figures.