Revitalization of Playground at Oso Beach

Sharbot Lake, Ontario

completeRecreationCC Top Up
Federal contribution
$16,950
Federal share33%

of $50.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Sep 1, 2009(actual)
Construction end
Apr 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Sep 30, 2009