Asset Management Program

Apsley, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,703
Federal share33%

of $11.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 4, 2007
200720082009
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of North Kawartha
Construction start
Jun 1, 2007(actual)
Construction end
Mar 30, 2009(actual)