Reconstruction of Anstruther Lake Road
Federal contribution
$1.1M
$1,132,784
Federal share33%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of North Kawartha
- Construction start
- Nov 2, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction end3 months earlyforecast Mar 30, 2011
Also in Apsley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27360 in the federal list. How to read these figures.