Back to projects

Municipality of French River - Asset Management

Noelville, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,215
Federal share33%

of $12.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 18, 2007(actual)
Construction end
Mar 6, 2008(actual)

Against the original forecast

  • Construction end3 months earlyforecast Jun 15, 2008

Also in Noelville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18046 in the federal list. How to read these figures.