Municipality of French River - Asset Management
Federal contribution
$4,215
Federal share33%
of $12.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of French River
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Mar 6, 2008(actual)
Against the original forecast
- Construction end3 months earlyforecast Jun 15, 2008
Also in Noelville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18046 in the federal list. How to read these figures.