Expansion of the Noëlville Landfill Site

Noelville, Ontario

completeSolid Waste ManagementCC
Federal contribution
$347,600
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Construction start
May 31, 2009(actual)
Construction end
Jul 31, 2012(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2009
  • Construction end21 months lateforecast Oct 31, 2010

Also in Noelville