Back to projects

Storm Piping and Sidewalk Construction

Charlottetown, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$520,798
Federal share32%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2007
Built

Approved 2 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Jul 1, 2007(actual)
Construction end
Oct 16, 2007(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 9, 2007
  • Construction end4 weeks earlyforecast Nov 15, 2007

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18057 in the federal list. How to read these figures.