Back to projects

Township of Huron-Kinloss Asset Management

Ripley, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,304
Federal share33%

of $12.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 7, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Huron-Kinloss
Construction start
Jun 15, 2007(actual)
Construction end
Feb 18, 2009(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Mar 31, 2009

Also in Ripley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18106 in the federal list. How to read these figures.