Replacement of Watermain and Reconstruction of Road
Federal contribution
$320,884
Federal share33%
of $962.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Huron-Kinloss
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 31, 2010
Also in Ripley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27112 in the federal list. How to read these figures.