Asset Management

St. Marys, Ontario

completeCapacity BuildingMRIF
Federal contribution
$5,241
Federal share33%

of $15.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 7, 2007
20072008
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Separated Town of St. Marys
Construction start
May 7, 2007(actual)
Construction end
Jan 11, 2008(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast May 30, 2007
  • Construction end2 months lateforecast Oct 31, 2007