Sundridge Asset Management

Sundridge, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,175
Federal share33%

of $9.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 27, 2007
2007200820092010
Built

Approved 7 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Sundridge
Construction start
Jun 27, 2007(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2007
  • Construction end18 months lateforecast Mar 31, 2009

Also in Sundridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18150 in the federal list. How to read these figures.