Back to projects

Brooke-Alvinston Asset Management

Brooke-Alvinston, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,797
Federal share33%

of $11.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 7, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 15, 2007(actual)
Construction end
Oct 23, 2009(actual)

Against the original forecast

  • Construction end12 months earlyforecast Oct 31, 2010

Also in Brooke-Alvinston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18201 in the federal list. How to read these figures.