Township of Scugog - Asset Management

Port Perry, Ontario

completeCapacity BuildingMRIF
Federal contribution
$6,015
Federal share33%

of $18.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 7, 2007
2007
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Scugog
Construction start
Jun 7, 2007(actual)
Construction end
Oct 13, 2007(actual)

Against the original forecast

  • Construction end8 months earlyforecast Jun 15, 2008