Revitalization of the Port Perry Downtown Waterfront
Federal contribution
$3.3M
$3,329,228
Federal share33%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Scugog
- Construction start
- Sep 25, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction end4.5 years earlyforecast Oct 1, 2015
Also in Port Perry
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24737 in the federal list. How to read these figures.