Construction of indoor soccer complex in Québec's Parc Chauveau
Federal contribution
$6.0M
$5,957,578
Federal share33%
of $17.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 23, 2008
2009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jul 28, 2008(actual)
- Construction end
- Jun 5, 2009(actual)
Also in Québec