Integrated Implementation of NWT Community Water Treatment Plants

Yellowknife, Northwest Territories

completeDrinking WaterMRIF
Federal contribution
$4.9M
$4,926,800
Federal share32%

of $15.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
MACA
Construction start
Jun 30, 2008(actual)
Construction end
Mar 21, 2012(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 5, 2007
  • Construction end12 months lateforecast Mar 31, 2011

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18573 in the federal list. How to read these figures.