Upgrade to Memorial Baseball Field to Meet Canada Games Standards

Charlottetown, Prince Edward Island

completeSportMRIF
Federal contribution
$113,545
Federal share33%

of $340.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20082010201220142016
Built

Approved 8.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Oct 9, 2007(actual)
Construction end
Jul 30, 2009(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 12, 2007
  • Construction end13 months lateforecast Jun 30, 2008