Village of St-Pierre-Jolys Lift Station and Sewer Upgrades
Federal contribution
$56,033
Federal share30%
of $185.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 8, 2007
200820092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of St. Pierre-Jolys
- Construction start
- Aug 6, 2008(actual)
- Construction end
- Dec 15, 2009(actual)
Against the original forecast
- Construction start12 months lateforecast Aug 1, 2007
- Construction end15 months earlyforecast Mar 31, 2011
Also in St-Pierre-Jolys