Lagoon Expansion and Wetland

St-Pierre-Jolys, Manitoba

completeWastewaterCWWF
Federal contribution
$635,255
Federal share21%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of St-Pierre-Jolys
Construction start
May 2, 2017(actual)
Construction end
Oct 13, 2017(actual)