Lagoon Expansion and Wetland
Federal contribution
$635,255
Federal share21%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of St-Pierre-Jolys
- Construction start
- May 2, 2017(actual)
- Construction end
- Oct 13, 2017(actual)
Also in St-Pierre-Jolys