O'Leary Recreational Fields
Federal contribution
$119,706
Federal share33%
of $362.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 26, 2008
20092010
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of O'Leary
- Construction start
- May 1, 2008(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2008
- Construction end2.2 years lateforecast Aug 30, 2008
Also in O'Leary