Access PEI O'Leary Upgrades

O'Leary, Prince Edward Island

underwayAdministration, Emergency and Public WorksCVRIS
Federal contribution
$644,156
Federal share80%

of $805.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2025
today
202420252026
BuiltForecast

Approved 20 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 2, 2026(actual)
Construction end
Oct 31, 2026(forecast)

Against the original forecast

  • Construction start2.4 years lateforecast Sep 30, 2023

Also in O'Leary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67616 in the federal list. How to read these figures.