Swimming Pool Solar Heating

Hudson Bay, Saskatchewan

completeGreen EnergyMRIF
Federal contribution
$21,027
Federal share25%

of $84.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 22, 2008
2008
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Hudson Bay
Construction start
Dec 14, 2007(actual)
Construction end
Oct 6, 2008(actual)

Against the original forecast

  • Construction start4 months earlyforecast Apr 1, 2008
  • Construction end6 months earlyforecast Mar 31, 2009

Also in Hudson Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18719 in the federal list. How to read these figures.