Back to projects

Town of Hudson Bay Aquatic Facility (Pool) Renewal/Replacement

Hudson Bay, Saskatchewan

completeRecreationCCRIS
Federal contribution
$639,120
Federal share40%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2021
2021202220232024
Built

Approved 8 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Hudson Bay
Construction start
Sep 1, 2022(actual)
Construction end
Jan 10, 2024(actual)

Also in Hudson Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57146 in the federal list. How to read these figures.