Town of Hudson Bay Aquatic Facility (Pool) Renewal/Replacement
Federal contribution
$639,120
Federal share40%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
2021202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Hudson Bay
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Jan 10, 2024(actual)